UXO
UXO survey along the Perugia–Città di Castello railway line.
A night survey covered 19 crossings along a 20 km railway route.
UXO / Railway / EPC & Infrastructure
Escolight Srl

THE CONTEXT
Unexploded ordnance (UXO) risk assessment and subsurface mapping over a 150,000 m² area commissioned by Escolight Srl, with Rete Ferroviaria Italiana (RFI) as the end client.
THE CHALLENGE
The project required a detailed assessment of the area designated for infrastructure works to ensure the absence of UXO and avoid interference with existing utilities.The goal was to perform a fully non-invasive, high-precision multisensor survey reaching depths of up to 7 meters, minimizing the need for intrusive methods such as coring or exploratory excavation.
OUTPUTS
Non-invasive multisensor survey using electromagnetic, magnetic and GPR instruments.
Data processing and anomaly targeting with DeepGeo.
Anomaly mapping with UXO compatibility assessment and a certified report.
EXPLORE MORE
YOUR NEXT PROJECT
Let’s discuss your site, the risk and the outputs you need.
Request a quote